L&T faces cost overrun of Rs3,000 crore
Posted on 3rd September 2014
Hyderabad: Larsen and Toubro Ltd (L&T), which is building the Rs.16,375 crore Hyderabad Metro Rail project, said on Tuesday it is facing a cost overrun of as much as Rs.3,000 crore on account of high interest cost and delays in execution.

“The project is at a critical stage,” said V.B. Gadgil, chief executive and managing director of L&T Hyderabad Metro Rail Pvt. Ltd, the unit that’s executing the metro rail project.

L&T has so far spent Rs.4,800 crore on the project, of which its equity contribution was Rs.1,500 crore.

L&T is investing around Rs.4,330 crore as equity—the single biggest investment so far on any project the firm has executed. The debt component is Rs.10,478 crore. The Union government has provided Rs.1,458 crore as viability-gap funding.

L&T raised debt from a clutch of 10 banks with the State Bank of India as the lead banker in March 2011 at a floating rate of interest of 10.5%.

But since then, interest rates have risen by two percentage points.

L&T said it has initiated a study to review the economic viability of the project, which was conceived in the undivided state of Andhra Pradesh.

L&T has so far completed around 28% of the project.

Problems of land acquisition have pushed the project timeline by at least 15 months behind schedule.

But the decision of the Telangana government that is seeking a realignment in at least two stretches at Sultan Bazaar and State Assembly could further delay the project.

“An independent committee will study technical, financial and legal implications of the realignment that was sought by the government,” said N.V.S. Reddy, managing director of Hyderabad Metro Rail Ltd—the agency that monitors Hyderabad Metro rail project on the behalf of the state government.

Reddy said the committee is expected to submit its report in a month and L&T will be informed about it.

Reddy declined to give details of cost escalation because of the changes.

Gadgil said L&T it is yet to receive any “official communication” from the government.

L&T has put pillars in some of the stretches, where the realignment was sought.

“All delays naturally will have impact on the cost,” Gadgil said.

L&T is also talking to India Infrastructure Finance Co. Ltd (IIFCL) to replace some of its existing debt to the tune of Rs.1,000 crore with cheaper and longer-tenure loans.

“We are in discussions with IIFCL,” said Gadgil, declining to give details.

Hyderabad Metro Rail is the biggest urban infrastructure project undertaken as a public-private partnership in India. The elevated Metro rail will cover 71.2km with three corridors comprising 66 stations.

The Metro network is to be constructed in five years, with L&T holding the concession for 35 years, extendable by an additional 25 years. The company can earn lease rentals from property development and advertising rights before the real estate is returned to the state government.

L&T won the bid to build the Metro rail network in July 2010 after the government in July 2009 cancelled the mandate given to Maytas Infra Ltd, which failed to tie up finances for the project. Maytas Infra was promoted by B. Ramalinga Raju, the founder of Satyam Computer Services Ltd, who in January 2009 confessed to having misstated accounts to the tune of Rs.7,136 crore, triggering India’s biggest corporate fraud investigation.

Related Companies: Larsen & Toubro Limited   

Other Latest News
Bharti Airtel defers Q2 results till Nov 14 over ambiguity on AGR verdict
Posted on 29th October 2019

Bharti Airtel said on Tuesday it has postponed its second-quarter earnings report to mid-November, as the wireless operator sought clarity on the court ruling asking telecom firms to cough up overdue payments to the government.

Shares of the company, which was expected to release its quarterly numbers later in the day, dropped 3.3 per cent in early trade.


Rupee slips 8 paise vs US dollar in early trade amid drop in oil prices
Posted on 7th October 2019
The rupee on Monday opened eight paise lower at 70.96 against the US dollar amid drop in crude oil prices and rise in Asian equities. The domestic unit on Friday closed almost flat at 70.88 against after the Reserve Bank of India (RBI) in a widely expected move cut key interest rates by 0.25 percentage point.

On a weekly basis, the local unit slumped by 32 paise.


LIC pips private insurers in first-year premium growth during April-August
Posted on 13th September 2019
In the first five months of the current financial year, first-year premiums of life insurance companies grew by 39.84% (year-on-year) at Rs 1.05 lakh crore as compared to Rs 75,588.35 crore in April-August of 2018-19.

Life Insurance Corporation of India (LIC) continued to grow at a faster pace compared to private insurance players, shows the data from the Insurance Regulatory and Development Authority of India (Irdai).


Apollo Hospitals rules out further stake sale
Posted on 13th September 2019
Apollo Hospitals Enterprise (AHEL) has ruled out further dilution of promoters’ stake in the company. The company also said its Rs 1,337-crore stake sale of Apollo Munich Health Insurance with mortgage major HDFC will be concluded by October. Following these stake sales, the promoters’ pledged position will come down from a high of 76% to 54% by October and eventually to 20% by November or December, company sources said here.

World trusts India on Kashmir, not us: Pakistan minister Ijaz Ahmed Shah
Posted on 13th September 2019
In a major embarrassment for Pakistan and its Prime Minister Imran Khan, the country's Interior Minister Ijaz Ahmed Shah, a retired brigadier, said the international community didn't believe Pakistan's narrative on Kashmir; instead it is India whose version is trusted.

» Post a FREE Classified Advertisement
Inviting Real Estate Agents, Job Placements Agents, Educational Institutes, Software Service Providers, Real Estate Builders, Marriage Bureaus, Travel Agents, Restaurant Owners, Health & Fitness Centers and other Local Businesses to Post a FREE Classified Advertisement on Cootera.com Classifieds Website.
Jobs in India India Real Estate Automobiles Matrimonials Beauty & Fitness

Add a comment for L&T faces cost overrun of Rs3,000 crore
Please only use this form to enter comments on the above company. All comments are reviewed before they are displayed on the web site. Not all comments may be displayed. Check back with us to see if your comments have been displayed.
If you want us to email the comments posted by users, please Subscribe by email
Name*
Comments*
Security Code*
 

Be the first person to write a business review for L&T faces cost overrun of Rs3,000 crore

Most Read News

More India News

  India Web Directory
Business Profiles
Yellow Pages
Photo Galleries
Global Web Directory
*** FREE India Classifieds
Order Premium Listings
Submit a Site
Business Reviews
Home
About us
Link to us
Advertise
Contact us
Google Search Keywords: India Catalog, IndiaCatalog, India Web Directory
    © 1999 - 2026 IndiaCatalog.com
    All Rights Reserved
Privacy Statement